2023 Road Paving Project

July 28th, 2023

July 28, 2023 Update
The road program is complete.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

July 11 Update:
Paving is complete in Section 1. Crews are now working is Section 2 (Beaumont Drive). Work is expected to take 2 days, weather permitting. Crews will then move to Section 3.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

Bray Brothers is scheduled to begin road paving on Monday, June 19. Work hours will be 7 a.m. – 5 p.m., Monday through Friday, weather permitting. No work will be scheduled on July 4.

All roads will remain open, but delays should be expected. Signs will be posted in each area before work begins. Please help by keeping vehicles and trash cans off the roadway.

The schedule below is subject to change. Check back for updates!

Section #1 – Milling expected to begin Monday, June 19 – followed by paving

  • Bailey Drive
  • Bakers Drive
  • Bankers Drive
  • Dunkin Drive

Section #2 – Milling estimated to begin Monday, July 3 (no work on July 4) – followed by paving

  • Beaumont Drive

Section #3 – Milling estimated to begin Monday, July 10 – followed by paving

  • Russell Court
  • Emerald Court

Section #4 – Milling estimated to begin Mid July

  • Township Complex

Thank you for your patience.