August 1 Updated Schedule
LOCATION | WEEK 5 8/5 – 8/9 | WEEK 6 8/12- 8/16 | |
1 | Brownsburg Road East | PAVE 8/6-8/7 | |
2 | Scott Drive | ||
3 | Creamery Road | ||
4 | Meadow View Drive | ||
5 | Sewer Plant Road | 8/7-8/9 |
July 31 Update: Paving has been cancelled due to threat of participation.
July 29 Update: Paving to resume on Brownsburg Road East on July 30.
Updated schedule as of July 18, 2024:
Beginning July 8, Harris Blacktopping will begin the 2024 Road Paving Project in Upper Makefield Township. The anticipated schedule is below. Please be advised that all work is weather-dependent and subject to change.
**** Schedule will be updated as work progresses****
**** NOTE: NO WEEKEND WORK****