2024 Road Paving Schedule

July 31st, 2024
   LOCATIONWEEK 5 8/5 – 8/9WEEK 6 8/12- 8/16
1Brownsburg Road EastPAVE 8/6-8/7 
2Scott Drive  
3Creamery Road  
4Meadow View Drive  
5Sewer Plant Road8/7-8/9 

Beginning July 8, Harris Blacktopping will begin the 2024 Road Paving Project in Upper Makefield Township. The anticipated schedule is below. Please be advised that all work is weather-dependent and subject to change.

**** Schedule will be updated as work progresses****

**** NOTE: NO WEEKEND WORK****