UPDATE:
COMPLETED: Cox Avenue, Lafayette Drive, Bunker Hill Drive
EXPECTED COMPLETION BY JUNE 19: Overlook Road, Riverview Road, Park Place, and General Sullivan Road
EXPECTED COMPLETION BY JUNE 26: Woodhill Road. Please note that Woodhill Road will require a temporary closure between Shannon Road and Highland Road during milling and paving.
All work is weather-dependent and subject to change.
Beginning Thursday, June 4, 2026, Bray Brothers, Inc. will begin the 2026 Road Paving Project in Upper Makefield Township. The anticipated schedule is below; however, all work is weather-dependent and subject to change.
Between 7:00 AM and 3:00 PM, roadway milling will take place on the following streets:
- Lafayette Drive
- Bunker Hill Drive
- Cox Avenue (from Lafayette Drive to Washington Street)
Residents are asked not to park on these roadways during these hours to allow the work to proceed safely and efficiently.