Road Program Begins

July 26th, 2021

July 21 Update: Paving will begin in the Terrell Drive neighborhood on July 22. The fire house parking lot will be milled this week and paved next week.

July 16 Update: During the week of July 19, work is anticipated to be completed on Canal Run East and West and will then begin on Terrell Drive.

July 9 Update: Paving will begin on Canal Run East and Canal Run West on Monday, July 12.

June 25 Update: Paving will begin in Bowmans Tower on Monday, June 28. The next phase of the project will be milling of Canal Run East and Canal Run West.

June 21 Update: Work will begin on Thompson Mill Road on June 22, weather permitting.

The 2021 Road Program will begin on June 18, 2021 in the Bowmans Tower subdivision.

After the subdivision is completed, Brownsburg Road and Thompson Mill Road will be the next stops. Updates will be posted as they become available.

Roads will be posted in advance, and all work is weather permitting.
Thank you for your patience.