ROAD PROJECT COMPLETE
Road Project Updates
All work is weather-permitting and subject to change.
August 26, 2020 – Crews will be working on Eagle Road (between 1250 – 1267 Eagle Rd)
August 20 – Milling and base repair following by paving begins in the neighborhoods of General Sullivan, General Knox and General Hamilton
August 17-19 – Pave Shires Crossing Development
August 13 – Continue paving Mt. Eyre Road
August 10-11 – Pave Valley View, Old Barn Court.
Motorists are advised to plan alternate routes.
August 7th – Clean-up Kings Grant Drive.
August 7th – Mill General Hamilton, General Sullivan and General Knox
Flaggers will be on site for traffic control.
Updates may be altered due to weather. Please check back for updates and vehicle restrictions.